Which of the following are inputs to a satellite tracking program?
- A. The satellite transmitted power
- B. The Keplerian elements Correct answer
- C. The last observed time of zero Doppler shift
- D. All these choices are correct
Why B is correct
Keplerian elements (semi-major axis, eccentricity, inclination, argument of perigee, RAAN, mean anomaly) define an orbit mathematically. Satellite tracking programs use these six parameters to compute position and velocity over time.
Why the others are wrong
- A: Transmitted power affects signal strength at the receiver but does not determine orbital position or trajectory.
- C: Zero-Doppler observation is a measurement you might take; it is not a standard input parameter for computing an orbit.
- D: Since the other two choices are not valid tracking inputs, 'all of these' cannot be correct.
Remember: Keplerian elements = the six numbers that define where a satellite is in space.
Previous (T8B05) · All T8B questions · Next (T8B07)
Take a free Technician practice exam
Study smarter on iPhone: progress tracking, smart review and cram mode, offline. Get RadioFluent free on the App Store.
Questions: NCVEC question pools (public domain), JSON via russolsen/ham_radio_question_pool (Apache 2.0, notices).